In the Puchberg plant, Rigips mainly produces powder products such as joint compound, plaster, and filler. New products are constantly being designed and developed.

In 2014, ESA was entrusted with the renewal of the mixing and dosing control system, the acceptance of raw materials, as well as the loading of semi-finished and finished products including SAP data exchange.

Full commitmentby ESA

Beginning of December, the production for assembly and commissioning was scaled down. According to the contract, production with the new ESAweight dosing station including data exchange had to be resumed within 14 days at the latest, at least to some extent.

On the part of ESA, work was carried out simultaneously with two IBN and two assembly teams in the individual plant areas. After just one week, the "semi-finished goods loading" could be handed over to Rigips.

Beginning of January, the official IBN was completed and transitioned to trial operation and production support.